The Delta Works (Dutch: Deltawerken) is a series of construction projects in the southwest of the Netherlands. They were built between 1954 and 1997 to protect a large area of land around the Rhine–Meuse–Scheldt delta from the sea.
The works include dams, sluices, locks, dykes, levees, and storm surge barriers in the provinces of South Holland and Zeeland.
The aim of the dams, sluices, and storm surge barriers was to shorten the Dutch coastline. This meant fewer dikes had to be raised. Along with the Zuiderzee Works, the Delta Works have been declared one of the Seven Wonders of the Modern World by the American Society of Civil Engineers.
Not to be confused with Delta Work.
History
Authorities knew about the flooding risks in the south of the country, but because of indecision and the Second World War, little action was taken. In 1950, two small estuary mouths, the Brielse Gat near Brielle and the Botlek near Vlaardingen, were dammed. After the North Sea flood of 1953, a Delta Works Commission was set up to find the causes and plan ways to prevent such disasters in the future. It revised some old plans and created the "Deltaplan." The commission also developed a framework called the 'Delta norm' to guide spending on flood defences, and the acceptable risks it set were written into the Delta Law. Some plans later changed, such as replacing a planned freshwater lake with a storm surge barrier, the Maeslantkering. Connections to the Haringvliet were dammed to limit salt water. Later plans also cover water quality, the leisure industry, shipping and nature, and the Room for the River projects gave rivers more space.
The most important area protected by the framework is the South Holland coast, which is home to four million people, most of whom live below normal sea level. Ten 'weak points' were upgraded because of expected sea level rise caused by global warming. During the building of the works, plans were also changed after public pressure. In the Nieuwe Waterweg, raising and widening the dikes would have destroyed important historic buildings, so a storm surge barrier was built instead and the dikes were only partly raised.
Environmental effects
The Delta Project, which the Delta Works are part of, was first designed at a time when people barely thought about the environment or how engineering projects affect nature. Awareness of the environment grew over the years, but the project had many effects on nature that cannot be undone.
Blocking the estuary mouths shortened the length of dykes that would otherwise have been needed to guard against floods. However, it also caused big changes to the water systems. The tides disappeared, so the change from salty sea water to fresh water became less gradual. Plants and animals suffered from this noticeable change. Rivers also filled up with polluted mud, because they no longer had an open path to the sea.
Project costs
The projects of the Delta Plan were paid for with the Delta Fund. In 1958, when the Delta law was accepted under the Delta Works Commission, the total cost was estimated at 3.3 billion guilder. This was equal to 20% of the national GDP at that time. The cost was spread over the 25 years it would take to finish the huge engineering project. Most of the money came from the national budget, with a contribution of 400 million guilder from the Marshall Plan. The Dutch natural gas discovery also helped pay for the project a great deal.
When the works were completed in 1997, the costs were set at 8.2 billion guilder. However, by 2012 the total costs were already set at around $13 billion.
Current status
The original plan was finished with the Europoortkering. This needed the building of the Maeslantkering in the Nieuwe Waterweg, between Maassluis and Hook of Holland, and the Hartelkering in the Hartel Canal near Spijkenisse. The works were declared finished in 1997, after almost forty years of work.
Because of climate change and rising sea levels, the dikes will eventually have to be made higher and wider. This is a long-term challenge against the sea. How much flood protection is needed, and what it will cost, is often debated and involves a complicated decision-making process. In 1995, it was agreed through the Delta Plan Large Rivers and Room for the River projects that about 500 kilometres of weak dike coverings would be reinforced or replaced along the Oosterschelde and Westerschelde between 1995 and 2015. After 2015, more upgrades are being made under the High Water Protection Program.
In September 2008, the Delta Commission, led by politician Cees Veerman, reported that the Netherlands would need a large new building program to strengthen its water defenses against the expected effects of global warming for the next 190 years. The plans included preparing worst-case evacuation plans and more than €100 billion, or $144 billion, in new spending through 2100. This money would pay for measures such as widening coastal dunes and strengthening sea and river dikes. The commission said the country must plan for the North Sea to rise by 1.3 meters by 2100 and by 4 meters by 2200.
Projects
The works that are part of the Delta Works are listed in order, by the year each one was finished.

Quiz time!
5 questions about Delta Works
Why were the Delta Works built?
Pictures
Keep exploring
This article is a child-friendly adaptation of the Wikipedia article on Delta Works, available under CC BY-SA 4.0.
Images from Wikimedia Commons. Tap any image to view credits and license.