A3 motorway (Romania)
The A3 motorway (Romanian: Autostrada A3) is a partly built motorway in Romania. It is planned to connect Bucharest with the Transylvania region and the north-western part of the country. When finished, it will be 596 km long. It will pass through Ploiești, Brașov, Făgăraș, Sighișoara, Târgu Mureș, Cluj-Napoca, Zalău and Oradea, and it will join Hungary's M4 motorway near Borș.
As of July 2025, about 204 km (127 mi) of the road is open. This includes the Bucharest – Ploiești motorway (62.5 km), the Râșnov – Cristian segment (6.3 km), the Târgu Mureș – Nădășelu segment (117 km) and the Biharia – Borș segment (5.4 km).
In January 2015, the section between Târgu Mureș and Câmpia Turzii was awarded for construction. It was split into two larger parts, with five lots that together add up to 51.8 km. By December 2021, all of these parts had been opened to traffic, except for Chețani − Câmpia Turzii (15.7 km). The contract for that stretch was ended in March of that year.
More work on the Nădășelu – Borș section (about 157 km in total) was put up for bidding between 2018 and 2019. Contracts were awarded for the Biharia − Borș segment (5.4 km, near the border with Hungary) in December 2018, the Chiribiș − Biharia segment (28.6 km) in June 2020, and the Zimbor – Poarta Sălajului segment (12.2 km) in the same month. Several other segments are still waiting to be awarded.
In August 2020, the 5.2 km segment between Comarnic South and Comarnic North, on the Comarnic − Brașov section (58.0 km), was put up for bidding again.
Bucharest – Brașov section
This motorway section, also called the "Snow Motorway", will cross the Carpathian Mountains along the Prahova Valley. The Comarnic – Brașov part is considered the hardest to build. The road will also connect to the future Terminal 2 of the Henri Coandă Airport and the future Bucharest – Chișinău motorway, through the Ploiești South-East (Dumbrava) interchange. The project was split into three larger sections. Work on the Bucharest – Ploiești section started on 15 March 2007, and the Bucharest Ring Road – Ploiești part opened on 19 July 2012. The last part through Bucharest opened on 14 December 2018.
Work on the Comarnic – Brașov section was due to begin in 2010, but the contract was cancelled after the Vinci–Aktor consortium withdrew. A new contract was awarded in December 2013 to a joint venture of Vinci, Strabag and Aktor, but the concession had been cancelled by June 2015. The project was tendered again later, and in early 2020 it was cancelled by the newly elected government. In December 2020, the Râșnov – Cristian segment opened.
| Bucharest – Brașov section | ||||||
|---|---|---|---|---|---|---|
| Section | Length | Period of construction | Contractor | Total cost | Financier | Status |
| Bucharest – Moara Vlăsiei | 19.5 km | May 2008 – August 2017 | Impresa Pizzarotti and Tirrena Scavi | 673.7 m lei | State budget | In service |
| Moara Vlăsiei – Ploiești | 43.0 km | July 2007 – August 2012 | Spedition UMB, Pa&Co Internațional, EuroConstruct Trading '98, Com-Axa | 883.7 m lei | State budget | In service |
| Ploiești – Comarnic | 48.6 km | 379.4 m euro (est.) | Planned | |||
| Comarnic – Brașov | 58 km | State budget | One segment in service, the rest - planned | |||
| Comarnic – Brașov section | ||||||
|---|---|---|---|---|---|---|
| Section | Length | Period of construction | Contractor | Total cost | Financier | Status |
| Section 1: Comarnic Sud – Comarnic Nord | 5.2 km | 68.6 m euro | Re-tendered | |||
| Section 2: Comarnic Nord – Bușteni | 16.3 km | Feasibility studies | ||||
| Section 3: Bușteni – Predeal | 12.8 km | Feasibility studies | ||||
| Section 4: Predeal – Râșnov | 15.2 km | Feasibility studies | ||||
| Section 5: Râșnov – Cristian | 6.3 km | October 2017 – December 2020 | Alpenside | 25.8 m euro | State budget | In service |
Brașov – Oradea section
This motorway section, known in Romanian as Autostrada Transilvania (Romanian), was split into three parts: the Brașov (Cristian) – Târgu Mureș (Ogra) segment, the Târgu Mureș (Ogra) – Cluj-Napoca West (Gilău) segment, and the Cluj-Napoca West (Gilău) – Oradea West (Borș) segment. Some parts are already open. The Câmpia Turzii – Nădăşelu segment opened in several stages between 2009 and 2018, and the Ungheni – Chețani segment opened in several stages between 2018 and 2020. The Biharia − Borș segment is also open. The Suplacu de Barcău – Borș segment has been under construction since 2004, but its contract was ended in May 2013, when the work was about 50% finished.
The project was first planned to be built by the American company Bechtel Corporation with its partner Enka. In 2004, the contract was given to Bechtel by Social Democrat Prime Minister Adrian Năstase without an open bidding process, citing "national security." The estimated cost rose from 2.8 billion € in 2003 to 4.7 billion € in a 2007 estimate. In 2011, the contract was renegotiated. Bechtel agreed to lower the building cost per kilometer by 50%, to 6.9 million euro, and would build only two segments, leaving the others open for tendering. The whole section was finished on December 15, 2023, when the last part between Chețani and Câmpia Turzii was completed. Traffic opened the following week, and people in Mureș county can now drive from Târgu Mureș by using the A10 in Turda and then the A1 motorway, all the way to the Hungarian border in Nădlac and onward to most of Europe.
Openings timeline
Many parts of the A3 motorway have opened since 2009. The first was the Turda to Cluj-Napoca West (Gilău) segment, which opened on 1 December 2009 and helps drivers go around the city of Cluj-Napoca. Other early parts were the Câmpia Turzii to Turda segment in 2010, the Bucharest Ring Road to Ploiești segment in 2012, and the Cluj-Napoca West to Nădășelu segment in 2018. More segments opened in 2018, 2020, 2021, and 2023, including Nuşfalău to Suplacu de Barcău and Cheţani to Câmpia Turzii. The newest opening in the list is Zimbor to Poarta Sălajului, which opened on 11 August 2026.
Progress on construction was recorded as of July 2020. Some other segments have contracts signed and are in the early stages of design and construction. One of these is the Nădăşelu to Zimbor segment, which is due in March 2027.
Exit list
| County | Location | km | mi | Destinations | |
|---|---|---|---|---|---|
| City of Bucharest | 6 | 3.7 | Gherghiței Street, Bucharest | ||
| Ilfov | Voluntari | 9 | 5.6 | Popasului Street, Voluntari | |
| Ștefăneștii de Jos | 13 | 8.1 | |||
| 16 | 9.9 | Short-term parking | |||
| 22 | 14 | ||||
| Moara Vlăsiei | 23 | 14 | Short-term parking, north-bound only | ||
| 25 | 16 | ||||
| 26 | 16 | Short-term parking, south-bound only | |||
| Snagov | 30 | 19 | |||
| Gruiu | 34 | 21 | Short-term parking | ||
| 38 | 24 | Bridge over Ialomița river | |||
| Prahova | Gherghița | 41 | 25 | Short-term parking | |
| 43 | 27 | ||||
| Drăgănești | 47 | 29 | Bridge over Prahova river | ||
| Dumbrava, Prahova | 49 | 30 | Short-term parking | ||
| 53 | 33 | ||||
| Râfov | 56 | 35 | Short-term parking | ||
| Bărcănești | 63 | 39 | Short-term parking | ||
| 68 | 42 | ||||
| Missing connection north towards Râșnov | |||||
| Brașov | Râșnov | 0 | 0.0 | ||
| 6 | 3.7 | ||||
| Missing connection north-west towards Târgu Mureș | |||||
| Mureș | Gheorghe Doja | 0 | 0.0 | DN15J – Târgu Mureș West | |
| Ungheni | 2 | 1.2 | |||
| 4 | 2.5 | ||||
| Sânpaul | 7 | 4.3 | Short-term parking | ||
| Iernut | 18 | 11 | |||
| Bogata | 31 | 19 | Bridge over Mureș river | ||
| Luduș | 32 | 20 | Short-term parking | ||
| 34 | 21 | Bridge over Mureș river | |||
| Chețani | 36 | 22 | |||
| Cluj | Câmpia Turzii | 0 | 0.0 | ||
| Mihai Viteazu | 9 | 5.6 | |||
| 9 | 5.6 | ||||
| 10 | 6.2 | Short-term parking | |||
| 12 | 7.5 | U-turn exit | |||
| 12 | 7.5 | Bridge over Arieș river | |||
| Petreștii de Jos | 21 | 13 | |||
| Săvădisla | 44 | 27 | U-turn exit | ||
| Florești | 46 | 29 | Short-term parking | ||
| Gilău | 51 | 32 | |||
| 52 | 32 | Bridge over Someșul Mic river | |||
| Gârbău | 61 | 38 | |||
| Missing connection north-west towards Zimbor | |||||
| Sălaj | Zimbor | 0 | 0.0 | ||
| Românași | 12 | 7.5 | |||
| Missing connection west towards Nușfalău | |||||
| Sălaj | Nușfalău | 0 | 0.0 | ||
| 2 | 1.2 | Short-term parking | |||
| Ip | 3 | 1.9 | U-turn exit | ||
| Suplacu de Barcău | 13 | 8.1 | |||
| Missing connection west towards Biharia | |||||
| Bihor | Biharia | 0 | 0.0 | ||
| 2 | 1.2 | ||||
| 4 | 2.5 | Short-term parking | |||
| 5 | 3.1 | ||||
| 1.000 mi = 1.609 km; 1.000 km = 0.621 mi Unopened | |||||

Quiz time!
5 questions about A3 motorway (Romania)
What is the A3 motorway planned to connect?