Safekipedia

Trans-Java Toll Road

Discoverer · ages 10+Adapted from Wikipedia
A view of the Jakarta–Cikampek Toll Road in Indonesia, a major highway that links the capital city of Jakarta with Cikampek to the east.

The Trans-Java Toll Road (Indonesian: Jalan Tol Trans-Jawa) is a tolled expressway network on the island of Java in Indonesia. It runs from Port of Merak in Cilegon, the main link between the island of Sumatra and Java, to Banyuwangi, the eastern end of the island and the main link between Java and Bali.

The road mainly runs along the northern coast of the island. Between Semarang and Surabaya, it runs through the centre and south of the island instead. It passes through five of the six provinces on Java, with DI Yogyakarta as the only exception. It connects major cities including Jakarta, Cirebon, Semarang, Solo, and Surabaya. The toll road is the land transportation backbone of the island and the most important toll road network in the country. It has a total length of 1,167 kilometres (725 mi).

The Trans-Java toll network was first conceived in full in 1995 by President Soeharto. It was meant to connect both ends of the island and help with distribution and general traffic between the major cities along the way. However, the 1997 Asian financial crisis, which affected the country, halted all development. The project was later revived by President Joko Widodo. Construction of the remaining sections started between 2014 and 2016. This revival was mainly due to the main Pantura road becoming increasingly congested, especially during the Eid and Christmas seasons.

Several sections of the toll road were completed in December 2018, fully connecting the sections between Port of Merak and Surabaya. The section connecting Surabaya and Probolinggo was completed a year later. As of 2023, the section between Probolinggo and Banyuwangi had its groundbreaking, with a targeted completion date of 2025.

The toll road is also linked to many other complementary toll networks. It is part of Asian Highway 2, which extends from Denpasar, Indonesia, to Khosravi, Iran.

History

During the Dutch colonial era, the colonial government ordered Governor-General Herman Willem Daendels to build a road connecting the two major ports of Anyer, part of modern-day Banten, and Panarukan in modern-day Situbondo. After Indonesian independence, the road became the main route linking Jakarta, Semarang, and Surabaya. It is more commonly known as Pantura (Jalur Pantai Utara, literally North Coast Road). It follows the northern Java coast instead of the old route through the Preanger cities of Bogor, Cianjur, Bandung, and Sumedang, before rejoining the coast in Cirebon. Over the years, the highway became crowded, especially during Eid or Christmas. It was open to everyone, including pedestrians, not just intercity traffic, and frequent roadworks slowed traffic even more.

To reduce congestion, President Suharto began building toll roads along the route in the 1980s, after Indonesia's first toll road, the Jakarta-Bogor-Ciawi (Jagorawi) Toll Road, was built. Soeharto also created a state-owned enterprise, PT. Jasa Marga, to run toll roads. The highway was finished in parts, including the Tangerang and Jakarta section in 1984 and the section between Surabaya and Gempol (near Pasuruan) in 1986. In 1992, the Tangerang–Merak section opened, linking the Merak port with Jakarta. Construction then slowed, and the 1997 Asian financial crisis later stopped many projects, though parts of the Jakarta Outer Ring Road were finished in 1995, along with the Palimanan-Kanci section that bypasses Cirebon. After Reformasi, construction continued under President Susilo Bambang Yudhoyono, and the government of Joko Widodo later pushed to finish the remaining sections, including the Cikampek-Palimanan section, with the Ministry of Public Works helping speed up the work. A new road was also built on the Porong-Gempol section to replace the one washed out by the Lapindo floods. The network was unveiled on 20 December 2018, connecting Merak and Surabaya. The section between Surabaya and Probolinggo was completed the next year. As of 2023, the only unfinished part is the 170 km section between Probolinggo and Banyuwangi, which is under construction slowly due to problems mainly related to land ownership.

Maps

Main route

Here is the map of the main route of the Trans-Java Toll Road in 2025.

Interconnection

The following is the updated interconnection map of the Trans-Java Toll Road as of July 2025.

Previous map

For reference, below is the Trans-Java Toll Road map as of July 2020.

Main route

Jakarta-Cikampek toll road is part of the whole Trans-Java toll road

The Tangerang–Merak Toll Road is 72.45 kilometres (45.02 mi) long and has operated since 1981, but it still loses money because fewer vehicles use it than expected. From 2005 to 2009, Astratel Nusantara, a subsidiary of Astra International, held the right to build and manage it. The Jakarta–Tangerang Toll Road is 33 kilometres (21 mi) long and is run by Jasa Marga. The Jakarta–Cikampek Toll Road is considered one of the most profitable in Java, collecting an average of 2 billion rupiahs (Rp) in tolls each day. It is often crowded because it connects Jakarta with Bekasi, Karawang, and routes to Bandung and the North Coast Road. The Cikampek–Palimanan Toll Road, which passes through Kalijati, was formerly the longest toll road in Indonesia. It lets drivers reach Cirebon from Cikampek in 1.5 hours instead of 3.5 hours. Driver mistakes, such as sleep-deprived driving and speeding, caused most of the accidents in its first weeks. The Palimanan–Kanci Toll Road is 26.3 kilometres (16.3 mi) long, and the Kanci–Pejagan Toll Road was sold to the Media Nusantara Citra (MNC) Group in 2012. By the end of 2015, Waskita Karya owned almost all of its shares. The Pejagan–Pemalang toll road was held by a company owned by Aburizal Bakrie before it was sold in 2012.

The Pemalang–Batang Toll Road and the Batang–Semarang Toll Road continue eastward across the north coast. The Semarang–Solo Toll Road runs through Ungaran and Salatiga. The Solo–Kertosono Toll Road connects to it at its west end and passes Karanganyar. The Kertosono–Mojokerto Toll Road passes Jombang, and the Mojokerto–Surabaya Toll Road reaches Waru. The Surabaya–Gempol Toll Road runs through Porong, but a section of the older Porong Toll Road was damaged by the Lapindo Mudflow in 2006. The Gempol–Pasuruan Toll Road and the Pasuruan–Probolinggo Toll Road follow. The Probolinggo–Banyuwangi Toll Road ends the route at the island's eastern tip and passes the Ketapang Ferry Terminal, a harbour that connects Java and Bali.

Complementary toll roads

Several smaller toll roads link to the main Trans-Java network around Jakarta. The Jakarta Inner Ring Road connects directly with the Jakarta–Cikampek Toll Road, and Jakarta Outer Ring Road 2 is planned to be a long route from Cengkareng to Tanjung Priok. The Jagorawi Toll Road was the first toll road in Indonesia. It was built to connect Jakarta and Bandung through Puncak, but it is now mostly used by tourists going to Puncak since the Purbaleunyi Toll Road opened. Other roads around Jakarta are planned or under construction, including the Cinere-Jagorawi Toll Road, the Cinere-Serpong Toll Road that will link South Tangerang with Depok, the Cibitung–Cilincing Toll Road, the Depok-Antasari Toll Road from South Jakarta to Depok, and the Bogor-Ciawi–Sukabumi Toll Road. The Cipularang Toll Road connects the Jakarta–Cikampek Toll Road with the Padaleunyi Toll Road and has cut car travel from Jakarta to Bandung to 2 hours. The Cisumdawu Toll Road will connect to Kertajati International Airport.

Further east, several toll roads serve the Surabaya area and beyond. The Surabaya–Gresik Toll Road connects Surabaya with Gresik, and the KLBM Toll Road is planned to link industrial areas near Surabaya. The Waru–Juanda Toll Road connects Surabaya with Juanda International Airport. The Pandaan-Malang Toll Road has had its first three sections opened, and it has shortened the trip between Pandaan and Malang to less than an hour. It will also help travel to Batu. The Solo–Yogyakarta-Kulonprogo Toll Road will connect the cities of Surakarta and Yogyakarta, and a 27 kilometer Semarang–Demak Toll Road is planned to be finished in 2022.

Impact

When the Trans-Java Toll Road was completed in 2018, connecting Jakarta and Surabaya, it led to a surge of intercity bus services in Indonesia. During this time, some of these bus services began operating a fleet of double decker busses.

Junction lists

Jakarta–Tangerang–Merak section

Distances and exit numbers are counted from the start of this section.

Jakarta–Cirebon–Semarang section

Distances are counted from the start of the toll road's name. Exit numbers are counted from the start of this section.

Semarang–Surakarta–Surabaya section

Distances are counted from the start of the toll road's name. Exit numbers are counted from the start of the Jakarta section.

Surabaya–Pasuruan–Banyuwangi section

The entire section is located in East Java.

Distances are counted from the start of the Jakarta section. Exit numbers are counted from the start of the Surabaya section.

ProvinceRegencyLocationkmmiExitNameDestinations
JakartaWest JakartaGrogol Petamburan0.00.00Tomang Interchange Jakarta Inner Ring Road – Soekarno-Hatta International Airport, Tanjung Priok, Pluit, Semanggi, Cawang, Cikampek
Tomang Toll Gate (westbound tolls only)
0Tomang RampTomang, Slipi, Grogol
Kebon Jeruk3.292.043Kebon Jeruk Toll GateKebon Jeruk, Kedoya
Kembangan5.933.686Meruya Toll GateMeruya, Kembangan, Joglo
7.304.547Meruya Interchange Jakarta Outer Ring Road – Soekarno-Hatta International Airport, Rawa Buaya, Kalideres, Meruya, Joglo, Ciledug
BantenTangerangKarang Tengah9.515.9111Karang Tengah Barat Toll GateKarang Tengah, Ciledug, Cipondoh
Pinang15.239.4615Kunciran Interchange Jakarta Outer Ring Road 2 – Soekarno-Hatta International Airport, Pinang, Cipondoh, Kunciran, Bintaro, Serpong
15.239.4615Kunciran Toll GateKunciran, Alam Sutera, Serpong
18.5111.5018Tangerang Toll GateTangerang, Pakulonan, Serpong
TangerangKelapa Dua20.9513.0221Karawaci Toll GateKarawaci, Binong, Legok
Curug26.5016.4726Bitung Toll GateBitung, Curug, Budiarto Airport
Cikupa31.6319.65Cikupa Toll Gate (Main toll gate/Border between Jakarta–Tangerang and Tangerang–Merak)
35.7822.2335Balaraja Timur Toll GateBalaraja, Tigaraksa, Cikupa
Balaraja39.1124.3039Balaraja Barat Toll GateBalaraja, Tigaraksa
SerangCikande52.3332.5252Cikande Toll GateCikande, Cikande Industrial Complex
Kragilan59.9537.2560Ciujung Toll GateCiujung, Kragilan
Ciruas64.1039.8364Walantaka Interchange Serang–Panimbang Toll Road – Rangkasbitung, Pandeglang, Tanjung Lesung
SerangCipocok Jaya72.2144.8772Serang Timur Toll GateSerang, Old Banten, Pandeglang
Taktakan77.6248.2377Serang Barat Toll GateSerang, Kramatwatu
SerangKramatwatu87.3654.2887Cilegon Timur Toll GateCilegon, Bojonegara
CilegonPurwakarta95.1959.1595Cilegon Barat Toll GateCilegon, Anyer, Carita, Krakatau Steel
Grogol98.4861.1998Merak Toll Gate Merak
1.000 mi = 1.609 km; 1.000 km = 0.621 mi
      Incomplete access
      Route transition
ProvinceRegencyLocationkmmiExitNameDestinations
JakartaEast JakartaJatinegara0.00.00Cawang Interchange Jakarta Inner Ring Road – Grogol, Tangerang, Soekarno-Hatta International Airport, Jatinegara, Ancol, Tanjung Priok
Makasar2.01.2Halim Utama Toll Gate (westbound tolls only)
2.091.302Halim Toll GateCawang, Halim Airport
Jagorawi Toll Road
4.022.504Pondok Gede Barat Toll GatePondok Gede, Jatiwaringin, Pondok Kelapa
West JavaBekasiPondok Gede8.004.978Pondok Gede Timur Toll GateJatibening, Cikunir
9.255.7510Cikunir Interchange Jakarta Outer Ring Road – Pondok Kelapa, Bintara, Tanjung Priok, Jatiasih, Jatiwarna
Jagorawi Toll Road
9.455.8710 Sheikh Mohammed bin Zayed Skyway – East Karawang, Bandung, Cikampek
South Bekasi13.108.1414Bekasi Barat Toll GateWest Bekasi, Pekayon, Kalimalang
East Bekasi16.5910.3116Bekasi Timur Toll GateEast Bekasi, Bulak Kapal, Bantar Gebang
BekasiSouth Tambun21.0613.0921Tambun Toll GateTambun, Setu, Mustika Jaya
Cikarang24.1815.0224Cibitung Interchange
29.4018.2730Cikarang Utara Toll GateCikarang Dry Port
30.8419.1631Cikarang Barat Toll GateNorth Cikarang, Lemahabang, Cibarusah
34.4321.3934Cibatu Toll GateCibatu, Jayamukti, Industrial Complex
37.0223.0037Cikarang Pusat Toll GateEast Cikarang, Pasirranji, Sukamahi
KarawangWest Telukjambe46.8429.1147Karawang Barat Toll GateWest Karawang, Rengasdengklok
47.4529.4847 Sheikh Mohammed bin Zayed Skyway – Jakarta, Bogor
Klari54.0433.5854Karawang Timur Toll GateEast Karawang, Klari
Cikampek66.9641.6167Kalihurip Interchange Cipularang Toll Road – Bandung
67.9342.2168Kalihurip Toll GateDawuan, Kalihurip, Bukit Indah
69.8843.42Cikampek Utama Toll Gate (Main toll gate)
PurwakartaBungursari72.5045.0572Cikampek Toll GateCikampek, Bungursari, Purwakarta
73.8045.86 Cikopo–Palimanan Toll Road
0.00.072Cikampek Toll GateCikampek, Bungursari, Purwakarta
Jakarta–Cikampek Toll Road
SubangKalijati25.5115.8598Kalijati Toll GateKalijati, Purwadadi, Sukamandi
Subang37.0623.03109Subang Toll GateSubang, Pamanukan, Lembang
IndramayuTerisi65.4240.65137Cikedung Toll GateCikedung, Cikamurang, Indramayu
MajalengkaKertajati79.6149.47152Kertajati Junction Cisumdawu Toll Road – Sumedang, Bandung
85.8553.34159Kertajati Toll Gate Kertajati International Airport, Kertajati, Majalengka
Sumberjaya101.9863.37174Sumberjaya Toll GateSumberjaya, Jatiwangi, Bandung
CirebonPalimanan116.0672.12188Palimanan InterchangePalimanan, Jatibarang, Indramayu
116.2672.24 Palimanan–Kanci Toll Road
0.00.0188Palimanan Toll GatePalimanan, Jatibarang, Indramayu
Cikopo–Palimanan Toll Road
Plumbon6.383.96194Plumbon Toll GatePlumbon, Plered, Trusmi
Talun15.229.46203Ciperna Toll GateCiperna, Cirebon, Kuningan
Astanajapura26.1616.26214Kanci Toll GateKanci, Astanajapura
26.3016.34 Kanci–Pejagan Toll Road
0.00.0214Kanci Toll GateKanci, Astanajapura
Palimanan–Kanci Toll Road
Ciledug18.3511.40233Ciledug Toll GateCiledug, Losari, Kuningan
Central JavaBrebesTanjung33.5720.86247Pejagan Toll GatePejagan, Prupuk, Purwokerto, Cilacap
33.7020.94 Pejagan–Pemalang Toll Road
0.00.0248Pejagan Toll GatePejagan, Prupuk, Purwokerto, Cilacap
Kanci–Pejagan Toll Road
Wanasari14.609.07263Brebes Barat Toll GateBulakamba, Klampok
Brebes20.6312.82268Brebes Timur Toll GateBrebes, Tegal
TegalTalang31.2419.41279Tegal Toll GateSlawi, Tegal, Guci
PemalangTaman64.0339.79312Pemalang Toll GatePemalang, Comal
64.1039.83 Pemalang–Batang Toll Road
Taman0.00.0312Pemalang Toll GatePemalang, Comal
Pejagan–Pemalang Toll Road
PekalonganBojong19.1411.89331Bojong Toll GatePekalongan, Kajen
BatangWarungasem29.7418.48341Batang Toll GateBatang, Pekalongan
Kandeman36.4822.67348Kandeman Toll GateBatang, Subah, Kandeman
36.6022.74 Batang–Semarang Toll Road
Kandeman0.00.0348Kandeman Toll GateBatang, Subah, Kandeman
Pemalang–Batang Toll Road
Gringsing23.9614.89371Gringsing Toll GateGringsing, Industrial Area
KendalWeleri36.1022.43384Weleri Toll GateWeleri, Batang
Pegandon47.0429.23395Kendal Toll GateKendal, Pegandon, Patebon
Kaliwungu60.4037.53409Kaliwungu Toll GateKaliwungu, Boja
SemarangNgaliyan64.8840.31Kalikangkung Toll Gate (Main toll gate)
71.3044.30419Krapyak InterchangeKrapyak, Ahmad Yani International Airport
Semarang Toll Road – Demak, Solo, Surabaya
1.000 mi = 1.609 km; 1.000 km = 0.621 mi
      Concurrency terminus
      Incomplete access
      Route transition
ProvinceRegencyLocationkmmiExitNameDestinations
Central JavaSemarangNgaliyan/West Semarang0.00.0419Krapyak Interchange Batang–Semarang Toll Road – Batang, Pemalang, Jakarta
West Semarang0.80.50Krapyak Toll Gate (Northbound tolls only)
2.451.52421Manyaran Toll Gate
Gajahmungkur7.834.87427Jatingaleh Toll GateJatingaleh, Simpang Lima, Jatidiri Stadium
Candisari10.116.28429Jangli InterchangeNorthbound (Section C) – Port of Tanjung Emas, Demak, Purwodadi
Southbound (Section B) – Tembalang, Srondol
Semarang–Solo Toll Road
Banyumanik0.00.0419 (433)Tembalang Interchange Semarang Toll Road – Kota Lama Semarang, Port of Tanjung Emas, Ahmad Yani International Airport
1.671.04Banyumanik Toll Gate (Main toll gate)
420 (434)Banyumanik RampTembalang, Diponegoro University
SemarangEast Ungaran11.186.95430 (444)Ungaran Toll GateUngaran, Gunungpati, Bandungan
Bawen23.1314.37442 (456)Bawen Toll GateBawen, Ambarawa, Magelang
Tengaran40.4325.12459 (473)Salatiga Toll GateSalatiga, Suruh, Tingkir
BoyolaliMojosongo62.4038.77483 (497)Boyolali Toll GateBoyolali, Klaten, Yogyakarta
KaranganyarColomadu73.6845.78493 (507)Colomadu Toll GateKartasura, Klaten
BoyolaliBanyudono74.1046.04 Solo–Kertosono Toll Road
KaranganyarColomadu0.00.0493 (507)Colomadu Toll GateKartasura, Klaten, Yogyakarta
Semarang–Solo Toll Road
Solo–Yogyakarta Toll Road
BoyolaliNgemplak5.153.20498 (512)Adi Sumarmo Airport Toll Gate Adisumarmo International Airport
11.447.11504 (518)Ngemplak Toll GateSolo
KaranganyarGondangrejo13.928.65506 (520)Gondangrejo Toll GateMojosongo, Gondangrejo, Purwodadi, Solo
Kebakkramat21.7113.49513 (527)Karanganyar Toll GatePalur, Karanganyar, Tawangmangu
SragenSidoharjo35.5922.11527 (541)Sragen Toll GateSragen, Gemolong, Purwodadi
Sambungmacan52.1932.43544 (558)East Sragen Toll GateMantingan, Gendingan, Purwodadi
East JavaNgawiNgawi86.7753.92579 (593)Ngawi Toll GateNgawi, Cepu, Magetan
86.8053.94 Ngawi–Kertosono Toll Road
0.00.0579 (593)Ngawi Toll GateNgawi, Cepu, Magetan
Solo–Ngawi Toll Road
MadiunMadiun23.6314.68602 (616)Madiun Toll GateMadiun Regency, Madiun, Magetan, Ponorogo
Balerejo32.1619.98611 (625)Caruban Toll GateCaruban, Karangjati
NganjukSukomoro67.8342.15646 (660)Nganjuk Toll GateNganjuk, Kediri, Blitar
JombangBandarkedungmulyo93.1257.86672 (686)Bandar Toll GateKertosono, Kediri
94.058.4 Kertosono–Mojokerto Toll Road
0.00.0672 (686)Bandar Toll GateKertosono, Kediri
Solo–Kertosono Toll Road
Tembelang14.418.95686 (700)Jombang Toll GateJombang, Ploso
MojokertoGedeg34.5521.47707 (721)Mojokerto Barat Toll GateGedeg, Mojokerto, Lamongan
Jetis39.8424.76712 (726)Penompo Toll GateMojokerto
40.0024.85 Surabaya–Mojokerto Toll Road
Jetis0.00.0712 (726)Penompo Toll GateMojokerto, Mojosari, Balongbendo
Kertosono–Mojokerto Toll Road
GresikWringinanom11.427.10724 (738)Wringinanom Interchange Krian–Legundi–Bunder–Manyar Toll Road – Gresik, Lamongan, Tuban, Krian, Wringinanom, Balongbendo
Driyorejo16.2510.10729 (743)Krian Toll GateKrian, Cerme, Mojosari
21.9513.64735 (749)Driyorejo Toll GateDriyorejo, Lakarsantri, Benowo
SurabayaKarangpilang28.4617.68Warugunung Toll Plaza (Main toll plaza)
29.8618.55742 (756)Karangpilang Toll GateKarangpilang, Wonokromo, Wiyung
SidoarjoTaman32.0919.94745 (759)Waru Interchange Surabaya–Gempol Toll Road – Gunung Sari, Sidoarjo, Pasuruan, Malang
Surabaya–Gresik Toll Road
Waru33.0020.51 Waru–Juanda Toll Road
1.000 mi = 1.609 km; 1.000 km = 0.621 mi
      Incomplete access
      Route transition

Quiz time!

5 questions about Trans-Java Toll Road

Question 1 of 5

The Trans-Java Toll Road links Sumatra to Java at its western end. What does its eastern end at Banyuwangi connect?

Keep exploring

This article is a child-friendly adaptation of the Wikipedia article on Trans-Java Toll Road, available under CC BY-SA 4.0.

Images from Wikimedia Commons. Tap any image to view credits and license.